Bheramara 410 MW Combined Cycle Power Plant

 

Power Plant Location

Bahirchar, Bheramara, Kushtia

Executive Agency

North West Power Generation Company Limited (An Enterprise of Bangladesh Power Development Board)

EPC Contractor

M/s. Marubeni Corporation, Japan

Financer

GOB & JICA

EPC Cost

USD: 178,788,328;
JPY: 10,237,497,008;
BDT: 2,562,922,636;
EUR: 8,510,300.
(Eqv. BDT. 251,998 Lac)

Total Project Cost

GOB: BDT 91,939.59 Lac plus
PA: BDT 322,108.42 Lac

EPC Contract Signing Date

16/03/2014

Manufacturer of GT and ST

Mitsubishi Hitachi Power Systems (MHPS)

Fuel Type

Dual Fuel (Natural Gas + HSD)

Generation Capacity

410 MW

Commercial Operation Date

09/05/2017 (Simple Cycle)
14/12/2017 (Combined Cycle)

ISO Certification

ISO 9001: 2015, ISO 14001:2015 & ISO 45001:2018 Certified