Sirajganj 225 MW Combined Cycle Power Plant (Unit-3)

 

 

Power Plant Location

Soydabad, Sirajganj

Executive Agency

North-West Power Generation Company Limited

EPC Contractor

Consortium of M/s. China National Machinery Import & Export Corporation (CMC), China and Fujian Electric Power Survey & Design Institute (FEDI), China

Financer

Standard Chartered Bank (SCB)
(ECA)

EPC Cost

USD 164.12 Million

Total Project Cost

USD 236.22 Million (Equ. BDT 182,856.87) (1USD=77.41 BDT)

EPC Contract Signing Date

12 July, 2015

Manufacturer of GT and ST

Siemens (GT)
Dongfang Electric Machinery Co. Ltd. (ST)

Fuel Type

Primary - Natural Gas, Alternative - HSD

Generation Capacity

220 MW

Commercial Operation Date

Simple Cycle: 09 Aug 2018
Combined Cycle: 20 Jan 2019


Share with :